Your factory has three working days left this month. That is not a figure of speech.
Between the Mid-Autumn Festival and National Day, Chinese production effectively stops from 25 September to 7 October 2026. Most founders find out when an email goes unanswered for a fortnight. The ones who planned for it locked their dates in six weeks ago.
Here is the calendar, what actually happens either side of it, and what is still worth doing this week.
When exactly do Chinese factories close in October 2026?
Two holidays, back to back, with a short working window between them.
- Mid-Autumn Festival. Friday 25 September to Sunday 27 September. Three days off.
- Working days. Monday 28, Tuesday 29, Wednesday 30 September. Three days.
- National Day, or Golden Week. Thursday 1 October to Wednesday 7 October. Seven days off.
- Back at work. Thursday 8 October.
- Mandated working Saturday. 10 October is an adjusted working day under the official 2026 calendar.
That last one matters. If a supplier tells you they will work the weekend of 10 October to catch up, they are describing a day the government has already booked. It is not extra effort. It is the make-up day for the holiday you just lost.
How long are factories really shut?
Officially seven days. Practically ten to fourteen.
Golden Week is the second biggest domestic travel event in China after Spring Festival. Line staff travel home, and a large share of the workforce in the manufacturing belts is not local. Office and QC staff tend to come back on time. Production capacity does not.
Then there is everyone your factory depends on. Your order does not move because your assembly plant reopened. It moves when the plating shop, the box printer, the label supplier and the component maker have all reopened, and they each run their own holiday schedule.
So do not ask your supplier whether they are closed. Ask two better questions.
- What date does the production line restart, not the office.
- What date do your material and component suppliers restart.
Get both in writing before Thursday. After that, nobody is answering.
What does Golden Week do to freight?
Carriers plan for it. That is the problem.
Roughly 283,000 TEU of capacity is being pulled from the market across the major alliances around the 2026 holiday period, through blank sailings and omitted services. Week 41, the week straight after the break, is the tightest. Fewer sailings and a backlog of cargo that has been sitting since late September is a reliable formula for rolled bookings.
The pattern repeats every year and it looks like this.
- Late September. A rush to load before the break. Space tightens, rates firm up, and small shipments get bumped in favour of large contracted volumes.
- The holiday itself. Ports keep running at reduced capacity. Trucking and customs brokerage in China largely stop.
- The first two weeks of October. Backlog clearing. Expect one to two weeks before schedules look normal again.
Less than container load cargo is first in line to be deprioritised, because consolidators need a full box before it sails. If your shipment is small and your date is tight, that is the risk to price in. The trade-off between a part container and a full one is covered in LCL vs FCL sea freight.
For planning, sea freight from the main Chinese ports to Sydney, Melbourne or Brisbane runs around 20 to 27 days port to port. Air is three to five days. Add clearance, unpack and delivery at the Australian end on top of both. If you are weighing one against the other, air freight versus sea freight walks through where the switch actually pays for itself.
What should you do this week?
Six things, in order of how much they cost you if you skip them.
- Get a written restart date. The line, not the office. And the same date from the component suppliers your order depends on.
- Pay the deposit now or accept an October start. A deposit landing on 29 September does not buy you a place at the front of the queue. It buys you a place behind everyone who paid on the 18th. Here is how to pay a Chinese supplier safely.
- Do not book an inspection for the last working week. Inspection agencies are as stretched as everyone else right now, and a rushed inspection is worse than a late one. The pre-shipment inspection guide sets out what a proper one covers.
- Raise every open quality question before Thursday. A defect found on 8 October costs you the whole month, because the fix goes into the queue behind the backlog.
- If the goods are finished, book freight for the 28 to 30 September window or plan on 8 to 12 October. The days in between are not a shipping option.
- Reset your delivery date in writing. Not a promise to try to catch up. A new date, in an email, that you can plan the rest of your business around.
A worked example, backwards from a January delivery
Say you want stock in a Sydney warehouse by 15 January.
- Sea transit, 20 to 27 days port to port. Call it 27.
- Clearance, unpack and delivery in Australia, 5 to 10 days. Call it 10.
- Post-holiday backlog, add a week to anything sailing in October.
So your vessel needs to depart China by roughly 5 December. Cargo ready and inspected by about 28 November. Production of 30 to 45 days means the line has to start by around 15 October, which means materials ordered and the deposit cleared before the holiday. That is this week, not next.
Miss that and January becomes February, and February is Chinese New Year. Spring Festival 2027 starts on 6 February and the official break runs nine days, the longest on record. The planning for that one starts in November, and the Chinese New Year 2027 shutdown guide has the dates.
Whether you absorb the cost of air freight to save the date, or take the later date and protect the cash, is a business call rather than a sourcing one. Kristy has written about that trade-off in how to manage cash flow in a product business.
What Golden Week means if you are going to the Canton Fair
The 140th Canton Fair runs across three phases this autumn.
- Phase 1. 15 to 19 October.
- Phase 2. 23 to 27 October.
- Phase 3. 31 October to 4 November.
Halls close for changeover on 20 to 22 October and 28 to 30 October, so there is no buyer access on those days. Which phase suits which product is set out in Canton Fair phases explained.
Here is the part that catches first-timers. Every factory you meet at that fair is one to three weeks behind its own schedule because of the break you just read about, and is heading into the pre-Christmas and pre-Spring-Festival crush straight after. A supplier quoting you a December delivery on the stand is quoting you a best case that assumes nothing else in their book slips.
Treat a fair in late October as sourcing for a first quarter production slot. If someone promises pre-Christmas on a new tooled product, ask them to put the ex-factory date in the quotation. Most will revise it.
Source Haus is on the ground for Phases Two and Three this year.
The mistake that costs the most
Treating the reopening date as the restart date.
Founders build their schedule from 8 October and the factory builds its schedule from full capacity, which is a week or more later. The gap is where a Christmas launch quietly turns into a February one.
Build your plan from 15 October. If the factory beats it, you are early. Nobody has ever been upset about being early.
The short version
Factories are closed 25 to 27 September and 1 to 7 October 2026. Three working days sit between the two. Real capacity does not return until roughly mid-October. Freight is tight either side. Anything not already locked in this week is an October start, and an October start is a February arrival once you add the backlog and the Australian summer.
If you want someone to look at your production dates and tell you honestly whether they still stack up, book a sourcing call.
Frequently asked questions
When is Golden Week 2026 in China?
National Day, or Golden Week, runs from Thursday 1 October to Wednesday 7 October 2026. It follows the Mid-Autumn Festival holiday of 25 to 27 September, leaving only three working days between the two breaks. Saturday 10 October is an adjusted working day under the official 2026 calendar.
How long do Chinese factories actually close for Golden Week?
The official holiday is seven days, but plan for ten to fourteen. Line staff travel home and many are not local, so capacity returns gradually rather than on day one. Component and material suppliers run their own schedules, and your order does not move until all of them are back.
Will Golden Week delay my shipment to Australia?
Probably, if it was due to move in early October. Carriers cut capacity around the holiday through blank sailings, and the week after the break is the most congested of the period. Expect one to two weeks of backlog clearing. Less than container load cargo is usually deprioritised first.
When should I book freight around Golden Week?
Four to six weeks ahead for ocean freight. If your goods are finished now, target the 28 to 30 September loading window or plan on 8 to 12 October. Booking during the holiday itself is not a realistic option.
Should I still go to the Canton Fair in October 2026?
Yes, but go looking for a first quarter production slot rather than pre-Christmas delivery. Every supplier at the fair is working through a Golden Week backlog and heading into the Spring Festival rush. Ask for the ex-factory date in writing on the quotation and most stated timelines will get revised.

Kristy Withers